Transfer test concept and infrastructure

Purpose

After project closure, tests are carried out for corrections and further developments. Therefore, the test concept and test infrastructure are transferred to the operating organization.

Basic idea

The maintenance and further development of the IT system continue even after project completion. Consequently, the test infrastructure and concept have to remain available.

HERMES-specific

The test concept and test infrastructure are transferred after the start of operation and before project closure. They are transferred by the project organization to those responsible for operation and further development in the case of the user, developer and operator.

Activities

  1. Adjust the test concept with test case descriptions and test data or update it with findings from the tests
  2. Inform and train those responsible
  3. Carry out formal transfer
  4. Produce a transfer report

Relationships

Module Task Task responsibility Outcome Involved in creation of outcome
Testing Transfer test concept and infrastructure Test manager Minutes Project manager

Outcomes